User stories: making them small enough

In terms of our company's evolution as we adapt Agile, we've moved toward having the work we need to do expressed as "user stories." But (in addition to learning how to write them) we've had a problem figuring out how long it takes to do a story (its "size") and then figuring out how many "stories" we can do in a sprint. So the question is - what size is the right size? Several people have been trying to answer that question within my company, and they've come up with this answer (which has been distributed around the team). I've edited it, but I didn't write it.
_____________________________________________________________

Sizeable should be Small.

And the Small is quite important. You want a number of stories in each sprint to :

· Increase the chance of getting as much work “done-done” as possible.
· The more stories you have, the smaller they are, which means more detailed acceptance criteria which means more accurate estimates and manageability.

Many of the teams working in my company have a problem breaking things down. Part of this is getting the user stories right so that it is clear what the Product Owner wants to achieve. The other part is having skill in being able to break things into smaller pieces. Some techniques (for web based work) are:

1. Separate user stories per site. Make the changes on one site and then have separate stories for each.
2. Progressive enhancement. Make a very simple feature in the first story and then add extra sub features in subsequent stories. (Stories are meant to be independent but in the case of an enhancement that builds on another story, clearly you have to be less rigid). For example, you may choose to first implement a new workflow in one story and then make adding validation as another story.
3. CRUD (Create Read Update Delete) may not need to be done at the same time. Consider releasing an input form first and then later adding the edit or delete functionality.
4. Data partitions – Some complex projects require the migration or cleaning of large amounts of existing data. One approach is to focus on the most valuable data partition first and then add additional stories to deal with less important cases and edge cases. This avoids projects stalling while the team gets hung up dealing with non valuable edge cases. For example, my company had a partner ask us to de-dupe all of our data in our Billing and Contracts DB. We knew that a project had stalled the previous year when trying to de-dupe the data so we took the approach of just focusing on the Billing Contacts. This was the highest value group to the PO and was easy for us to de-dupe.
5. Evolution. Sometimes it’s better to start from scratch. But most of the time at my company, we are enhancing an existing piece of functionality. When creating new workflows, there is an option to “evolve” over a number of sprints - basically, take an existing workflow and tackle small stories one at a time.
6. Iterate. If your acceptance criteria sound like they will require a lot of work, sometimes all you need to do is take the criteria and turn them into child stories. When you do this, you then realize how big a single acceptance criterion is and you can add more criteria to it to help with the estimates and everyone’s understanding of the project. Sometimes you might find that you need to break these stories down even further. You can use record cards on a table in the backlog workshop and arrange them into a hierarchy if it helps. Visualizing the problem in this way can really help.
7. Draw pictures. Draw pictures of how new pages/controls/reports might looks. You can then use a red marker pen to outline sub elements and ask yourselves “can this bit of the pages be split of into a separate user story?”

Slicing isn’t easy. It takes time to rotate the problem in your mind and come up with different solutions. Sometimes, setting aside some time in a team’s backlog session to explicitly brainstorm and discuss different options helps; sometimes taking it away and thinking about it on your own is the way to go. Some good rules of thumb when slicing are:

1. Have we sliced it small enough so that we can fit more than one story in a sprint (3+ is ideal)?
2. Can this story be released on its own and give value for the Product Owner?

Generally brilliant user story presentation (not really about slicing):

http://www.mountaingoatsoftware.com/system/presentation/file/97/Cohn_SDWest2009_EUS.pdf

In depth article on splitting:

http://radio.javaranch.com/lasse/2008/06/13/1213375107328.html

1 comment:

  1. The appropriate size for the story depends on the purpose and the audience.

    For detailed scheduling and as direct input into development, small user stories can be helpful, as they foster a lot of scheduling and prioritization options. They also help spec things out at the developers' level.

    However, as artifacts for understanding the problem to be solved and keeping an orientation to user and market needs, small user stories are detrimental. Someone needs to document, track, and ensure satisfaction of stories (or epics) that really matter to the user.

    For example, a user doesn't care about registration or logging into a system. Or, more precisely, the user would prefer not to have to go through such tasks. To achieve security and other ends (which do matter to the user), designers choose to require the users to go through registration and log-in. But if we could achieve those same ends without putting such a burden on the users, then we should do it.

    Thus a "User Registers" or "User Logs In" story is oriented around development and not around user needs. We also need stories or epics that capture true user needs. And we need to test them, so that we not only ensure the implementation follows the design, but that the system actually solves users' problems.